#1 已发布: 2023/12/19 23:55:54
Fikret Atalay

Fikret Atalay

2个赞,共24个帖子。

组: User

Hi all, I am putting together a quick worksheet to calculate factor of safety against soil liquefaction triggering. As I have been going step-by-step and defining the various variables, I noticed that all the calculations take place more or less instantaneously, whereas the last variable I defined (N1_60cs) seems to take a relatively long time to calculate (approximately 12 seconds on my machine). The worksheet I have so far is attached.

Any thoughts as to what is causing this? Thanks in advance!

Seismic Site Class & Liquefaction Potential.sm (124.01 KiB)已下载 1532 次。
#2 已发布: 2023/12/20 00:50:59
Davide Carpi

Davide Carpi

1,443个赞,共2,936个帖子。

组: Moderator

Hi,

select all > optimization > numeric

AND EITHER

z:z

z def z.png

OR

z:+line(...)

z plus.png


This is because z:line() is a procedure (something like a function, but for variables); it doesn't evaluates in place on definition, hence is completely calculated from scratch every time you need z, z[j], etc....
Using a + between the definition operator and the line() function, you don't have anymore a procedure; using z:z, it evaluates once from that point onwards.


Seismic Site Class & Liquefaction Potential_num.sm (124.85 KiB)已下载 1506 次。
If you like my plugins please consider to support the program buying a license; for personal contributions to me: paypal.me/dcprojects
#3 已发布: 2023/12/20 01:01:15
Fikret Atalay

Fikret Atalay

2个赞,共24个帖子。

组: User

Perfect, that works!

Much appreciated as always!
#4 已发布: 2023/12/20 01:23:18
Davide Carpi

Davide Carpi

1,443个赞,共2,936个帖子。

组: Moderator

You're welcome!
If you like my plugins please consider to support the program buying a license; for personal contributions to me: paypal.me/dcprojects
#5 已发布: 2023/12/20 01:30:22
Jean Giraud

Jean Giraud

983个赞,共6,866个帖子。

组: User

Your last for/loop, as given, takes 32 s
isolate the three components
a:=eval(a) , b:=eval(b) ...
timing drops 4 s
#6 已发布: 2023/12/20 02:07:23
Alvaro

Alvaro

1,139个赞,共1,805个帖子。

组: User

Hi. This is another option, without numeric optimizations. You don't need to use line in your calculations. As Davide says, that makes the calculations faster to SMath.

Seismic Site Class & Liquefaction Potential.sm (122.56 KiB)已下载 1577 次。


Bes regards.
Alvaro.
#7 已发布: 2023/12/20 03:15:47
Fikret Atalay

Fikret Atalay

2个赞,共24个帖子。

组: User

Thank you, Alvaro! I like having the lines because it makes it clearer as to which parameter I am defining. I just didn't realize it was slowing it down so much (although putting + in front of the lines makes the problem go away - sort of a win-win!).

Thanks again.

Wrote

Hi. This is another option, without numeric optimizations. You don't need to use line in your calculations. As Davide says, that makes the calculations faster to SMath.

Seismic Site Class & Liquefaction Potential.sm (122.56 KiB)已下载 1577 次。


Bes regards.
Alvaro.



#8 已发布: 2023/12/20 03:16:36
overlord

overlord

600个赞,共1,381个帖子。

组: Moderator

Wrote

Hi. This is another option, without numeric optimizations. You don't need to use line in your calculations.


Another issue is, all calculation can be done under one for() loop.
If data matrices is much longer and not 10, this would benefit too.
However, the way it is written look much nicer and cleaner.
#9 已发布: 2023/12/20 12:07:29
Alvaro

Alvaro

1,139个赞,共1,805个帖子。

组: User

Wrote

I like having the lines because it makes it clearer as to which parameter I am defining.



Hi. You can eliminate all the for loops using the SMath index vectorization, which work more or less like the same concept in matlab, with cases() for having some visual separation

Clipboard01.png

Seismic Site Class & Liquefaction Potential v2.sm (119.62 KiB)已下载 1568 次。

Best regards.
Alvaro.